Contabo Server Status
All
Interruptions
Running Maintenances
Scheduled Maintenances
Finished Maintenances
Interruptions
08.09.2026 11:00 am (UTC+2) Degraded Performance - CEPH Cluster: non-critical
Estimated duration: 900 minutes
We are currently addressing performance issues affecting our Object Storage cluster. The Object Storage product remains fully functional.
As a precaution, automated backups to this cluster have been temporarily paused. Existing backups are unaffected, and restores continue to operate normally.
A fix is already underway. We expect the cluster to be fully operational within the next few days and are closely monitoring progress. Once resolved, automated backups will resume, and backup status will remain visible via the Customer Control Panel throughout.
We will provide further updates as they become available.
As a precaution, automated backups to this cluster have been temporarily paused. Existing backups are unaffected, and restores continue to operate normally.
A fix is already underway. We expect the cluster to be fully operational within the next few days and are closely monitoring progress. Once resolved, automated backups will resume, and backup status will remain visible via the Customer Control Panel throughout.
We will provide further updates as they become available.
Running Maintenances
16.09.2026 11:11 am (UTC+2) No running maintenance
There are currently no maintenances running in our data centers.
Scheduled Maintenances
| Start | 10.10.2026 03:00 am (UTC+2) |
| Estimated duration | 840 minutes |
| Affected systems | Singapore 2 |
| Description | Scheduled Maintenance — Singapore 2 October 10, 2026 · 03:00 CET – October 10, 2026 · 17:00 CET We will be performing scheduled maintenance on the power infrastructure in our Singapore 2 data center. During this maintenance window, servers in this location will be temporarily unavailable. |
Finished Maintenances
16.09.2026 11:11 am (UTC+2) No finished maintenances
No maintenances have been performed.
